Construction
Page Navigation
Roosevelt Elementary School-MOD
Roosevelt Elementary School-MOD
Start Date: June 2012
Finish Date: August2012
Project Description: This project is a Modernization under a single prime contractor. Don Krotee Partnership Architects has completed the design for the Roosevelt Elementary School MOD project.
· Exterior ADA Accessibility upgrades
· Elevator Upgrades
· Interior ADA Accessibility upgrades
· New lighting at computer lab and surrounding hallways
· Bathroom ADA and aesthetic upgrades
· New carpet throughout building to district standards
· Repaint all interior surfaces
· New Ceiling tiles throughout
· Remodel Multi-purpose room
· New Fire Alarm System
· Remove and replace old cork board ceiling in hallways
· Remove and replace exterior wooden sidelights with new storefront sidelights
· New iron fencing and gates
· Classroom Technology